Buyer pack · version 1.0

Buy a TM44 inspection on comparable terms

Use one air-conditioning plant schedule, define the control boundary once and give every accredited assessor the same report, lodgement and access requirements.

Create an assessment result first
The standard

A comparable quote must answer five things

  1. Who is the named accredited energy assessor and what current scheme entry and level apply?
  2. Which buildings, systems, indoor units, outdoor units, chillers, AHUs and controls are included?
  3. How will effective rated output and units under common control be established?
  4. What site inspection, calculations, recommendations, report and lodgement are included?
  5. What maintenance, repairs, access equipment, travel, VAT and follow-up are excluded?
01

Information to assemble before requesting quotes

Mark unknown items explicitly. Discovery can be priced; hidden assumptions cannot be compared.

  • Person controlling the system and building or lease responsibilities
  • Site and building schedule with access contacts
  • Plant inventory with make, model, output, identifiers and served areas
  • How units are grouped, operated and controlled
  • Chillers, AHUs, ventilation systems and control strategy
  • Previous TM44 report, register reference and recommendations
  • Maintenance, energy, operating-hours and comfort records
  • Inaccessible plant, security, inductions and target report date
02

Project brief

Business and site: ______________________________________________

Reason for commissioning: first / periodic / new installation / change or event

Equipment and identifiers: ______________________________________

Use, process or operating conditions: ______________________________

Documents available: ___________________________________________

Sites and areas in scope: ________________________________________

Access and shutdown constraints: _________________________________

Target visit and report date: _____________________________________

Required quotation format

  • Who is the named accredited energy assessor and what current scheme entry and level apply?
  • Which buildings, systems, indoor units, outdoor units, chillers, AHUs and controls are included?
  • How will effective rated output and units under common control be established?
  • What site inspection, calculations, recommendations, report and lodgement are included?
  • What maintenance, repairs, access equipment, travel, VAT and follow-up are excluded?
03

Competence and evidence questions

Competence is specific to the equipment, system and judgement being bought. Ask about the proposed person, not only the company.

  1. Who is the named assessor and which accreditation scheme, number and level apply?
  2. Is the scheme entry current and suitable for the systems in the brief?
  3. What comparable split, VRF, chiller, AHU and controls experience can they evidence?
  4. Who will attend, review and lodge the report?
  5. Can they provide a redacted comparable report with plant scope and recommendations?
  6. How are inspection findings separated from maintenance or remedial sales?
  7. What professional indemnity and public liability evidence applies?
04

Comparable quote scorecard

Comparison pointProvider AProvider BProvider C
Named assessor and scheme evidence
Assessor level and system experience
Person in control and building boundary
Unit and central-plant schedule
Effective rated output method
Controls and maintenance evidence
Accessible and excluded equipment
Efficiency findings and recommendations
Report and lodgement included
Travel, access, VAT and follow-up
Total comparable fee

Do not add the scores blindly. Missing competence, equipment scope or statutory reporting can be a stop condition rather than a small disadvantage.

05

Report acceptance check

  • Correct person in control, site and building boundary
  • Every included system and unit is identifiable
  • Effective rated output and grouping are explained
  • Accessible equipment and controls inspected are recorded
  • Sizing, operation and maintenance evidence are addressed
  • Recommendations are specific and understandable
  • Limitations and inaccessible plant remain visible
  • Lodged report reference and next due date are supplied

Primary basis: GOV.UK air-conditioning inspection guide .