Create an assessment result first
The standard

A comparable quote must answer five things

  1. Who is the named inspector and what comparable installation experience can they evidence?
  2. Which boards, circuits, premises and inaccessible areas are included?
  3. How will safe isolation, sampling and operational shutdowns be agreed?
  4. Will the fee include test schedules, coded observations and the signed EICR?
  5. What travel, parking, VAT, remedials, return testing and out-of-hours work are excluded?
01

Information to assemble before requesting quotes

Mark unknown items explicitly. Discovery can be priced; hidden assumptions cannot be compared.

  • Dutyholder and lease or ownership boundary
  • Site addresses and access contacts
  • Distribution board and main-switch counts by site
  • Approximate circuit count and known three-phase or specialist systems
  • Previous EICR, circuit schedules, installation certificates and open defects
  • Faults, damage, modifications and harsh-environment areas
  • Permitted isolation windows, critical loads and escorts
  • Required report and action dates
02

Project brief

Business and site: ______________________________________________

Reason for commissioning: first / periodic / new installation / change or event

Equipment and identifiers: ______________________________________

Use, process or operating conditions: ______________________________

Documents available: ___________________________________________

Sites and areas in scope: ________________________________________

Access and shutdown constraints: _________________________________

Target visit and report date: _____________________________________

Required quotation format

  • Who is the named inspector and what comparable installation experience can they evidence?
  • Which boards, circuits, premises and inaccessible areas are included?
  • How will safe isolation, sampling and operational shutdowns be agreed?
  • Will the fee include test schedules, coded observations and the signed EICR?
  • What travel, parking, VAT, remedials, return testing and out-of-hours work are excluded?
03

Competence and evidence questions

Competence is specific to the equipment, system and judgement being bought. Ask about the proposed person, not only the company.

  1. Who will inspect and sign the report?
  2. What electrical inspection and testing competence covers this installation type?
  3. How will safe isolation and any live-testing exception be controlled?
  4. Which instruments and calibration records apply?
  5. Who reviews coding, limitations and test schedules?
  6. Can they show a redacted comparable EICR?
  7. What current insurance covers this work?
04

Comparable quote scorecard

Comparison pointProvider AProvider BProvider C
Named inspector and competence
Premises and board schedule
Circuit count and additional-circuit rate
Isolation and shutdown plan
Inspection and test extent
Sampling and limitations
Circuit test schedule
Coded defects and overall outcome
Dangerous finding response
Report delivery date
VAT, travel, repairs and return visit
Total comparable fee

Do not add the scores blindly. Missing competence, equipment scope or statutory reporting can be a stop condition rather than a small disadvantage.

05

Report acceptance check

  • The installation boundary and responsibility are stated
  • Included boards and circuits can be identified
  • Test results and limitations are traceable
  • Coded observations explain the finding
  • Immediate danger was escalated and made safe as agreed
  • Overall condition and recommended next inspection are recorded
  • Remedial work is quoted separately
  • The report does not claim a universal statutory five-year interval

Primary basis: HSE electrical safety guidance .